The Federal Government is set to take decisive action on the Benin-Asaba highway following months of delays and worsening road conditions, with the Ministry of Works moving to bring in a new contractor.

The Federal Controller of Works, Edo State, Engr. Babatunde Tajudeen disclosed this in Benin City on Monday, September 7, 2026, disclosing that the Minister of Works, Engr. Dave Umahi has ordered urgent intervention on the 125-kilometer road.
The highway, which runs from Ring Road Roundabout in Benin to Summit Junction in Asaba, links the South-South, South-East and South-West and remains critical for trade and movement.
It was concessioned to Benin-Asaba Expressway Concession Company Limited (BAECC) in 2023 under the Highway Development and Management Initiative (HDMI) – a 25-year Design, Finance, Build, Operate and Transfer agreement signed on May 23, 2023.
Following poor execution and abandonment of the project, angry residents protested over the bad state of the road on August 16, 2026.
Nine days later, Minister Umahi and Edo Governor, Monday Okpebholo visited the site for on-the-spot assessment.
The Minister accused BAECC of gross breach of the concession agreement, citing scarification of stable asphalt without reconstruction, use of allegedly unqualified personnel, lack of capacity, slow pace and substandard work, and poor traffic management that caused gridlocks in December 2025 and from Aug 19, 2026.

According to Engr. Tajudeen, stripping the road surface without immediate reconstruction exposed it to rain, worsening the damage. Some portions, he noted, may now require *Continuous Reinforced Concrete Pavement instead of asphalt.
The Controller however clarified that the concession has not been terminated legally yet, adding that the Minister has proposed a mutual termination and requested that another competent Federal Works contractor be deployed immediately.
BAECC was also directed to restore scarified sections to their pre-construction state of 16 months ago.

“Two weeks after the Minister’s engagement, no meaningful intervention has been recorded. The Ministry is now intensifying efforts to bring in an alternative contractor within its legal powers,” he said.
Engr. Tajudeen who appealed to motorists, residents and transport operators to be patient, stressing that government understands the road’s importance, praised President Bola Tinubu for prioritizing infrastructure and Minister Umahi for his frequent monitoring visits to Edo.
“The Benin-Asaba Highway will not be left in its present state. The Federal Ministry of Works is committed to a lasting solution and restoring the road to a safe, motorable condition,” he assured.

The Ministry urged all road users to remain calm while processes to engage a credible contractor are concluded.